Rio Tinto stock: Power deal clears Line 4 restart path
Published on 11/17/2026 at 17:44 | Editorial responsibility: Rafael Müller, Editor-in-Chief AD HOC NEWSWhat the restart means
- The smelter is expected to return to about 360,000 tonnes of annual capacity.
- Full production is targeted for December 2027.
- The agreement is designed to reduce winter power use and protect New Zealand's energy security.
Rio Tinto signed a three-and-a-half-year electricity agreement with Contact Energy on November 17, 2026, clearing the way for the restart of Line 4 at the Tiwai Point aluminium smelter in New Zealand. The company said the 50MW contract will support predominantly renewable power for the additional smelting capacity, according to Business Wire.
Line 4 restart timeline
Operational preparations and commissioning are expected to begin in October 2027, with full production targeted for December 2027. Line 4 has been idle since April 2020 after the COVID-19 pandemic disrupted global industrial markets.
Once fully operational, the restart is expected to add approximately 30,000 tonnes of aluminium production a year. Rio Tinto said this would restore the smelter to production capacity of approximately 360,000 tonnes per year and add approximately three percent to its smelting capacity across Australia and New Zealand.
Power terms and investor context
The agreement is structured to reduce electricity supply to 25MW during winter months, which Rio Tinto said will protect New Zealand's broader energy security. The contract provides bridging power while the parties continue work on a longer-term power purchase agreement that could support Line 4 for at least two decades.
Based on current global spot aluminium prices, Rio Tinto said the additional output could generate around NZ$100 million in annual export revenue for New Zealand. The estimate is tied to prevailing aluminium prices and is not a company earnings forecast.
Broader developments are covered in Current market reports.
More company coverage is available in More news and analyses on Rio Tinto stock.
Rio Tinto company facts
- Company: Rio Tinto plc
- ISIN: GB0007188757
- London ticker: RIO
- Announcement date: November 17, 2026
- Project: Tiwai Point aluminium smelter, New Zealand