Vulcan Energy Adds Seismic Survey Near BASF and Up to Three Landau Wells as Lionheart Build Advances
Published on 11/23/2026 at 22:01 | Editorial boerse-global.deVulcan Energy has mapped out a busy multi-front work programme across Germany's Upper Rhine region, pairing early-stage exploration in the Vorderpfalz with an expansion of its existing Landau geothermal plant and steady civil works at its flagship Lionheart lithium site.
Under a joint announcement with BASF on 18 November, Vulcan plans 3D seismic surveys in the Vorderpfalz for summer 2027. The work is exploratory in nature, and no decision on drilling or the siting of facilities has yet been taken. BASF, for its part, could draw on geothermal heat to generate steam without CO? emissions.
Expansion plans at the Eutzinger Straße site
At its operating geothermal facility on Eutzinger Straße in Landau, Vulcan presented expansion proposals on 11 November. Beyond a relief well that has already been approved, the company intends to sink up to three further deep wells. Drilling is not expected before autumn 2027 at the earliest.
Should investors sell immediately? Or is it worth buying Vulcan Energy?
The neighbouring Landau-Ost block, which borders the Lionheart project, is covered by a five-year licence to explore for both geothermal heat and lithium. Vulcan is currently evaluating subsurface data and is targeting an initial resource estimate for the first quarter of 2027. A feasibility study is to follow that estimate, after which the company will weigh development options — among them a possible tie-in of Landau-Ost to Lionheart.
Second rig arrives as Lionheart stays on budget
At the commercial lithium extraction plant itself, construction is now under way, with foundations, concrete work, access roads and site drainage all part of the package. Vulcan says the project remains within its time and cost framework and is aiming for first production in the second half of 2028.
The company has also brought its second own drilling rig to the Trappelberg drilling site to support the drilling programme. Roughly €51 million has been invested in the two rigs, according to Vulcan. With the start of construction, the company says it has reached its key implementation milestones for 2026.